Arlington Reservoir Phase II Project
The Town of Arlington has secured the services of Kyle Zick Landscape Architecture, Inc. (KZLA) to begin the design of Phase II renovations to the Arlington Reservoir. Following the guidance of the Reservoir Master Plan phase two of the project will include, but is not limited to, renovations and improvements to the following areas:
  • Parking Lot
  • Beach Entrance
  • Bathing Beach and Grass Area of the Beach
  • Bathhouse
  • Playground
  • Perimeter Trail
  • New site amenities like benches, life guard stands, bike racks, etc.
  • Improved accessibility and access through the landscape
  • Fishing Areas
  • Bird Viewing Areas & Other Passive Recreation Improvements
In order to assist us in the design process, the Park Commission and KZLA encourage the public to participate.  As we are designing, we are hoping to get as much input a possible from the community. We have created an on-line survey and would like to ask some specific questions about how you use the Res, its trails, the park amenities, the swimming beach, etc. You may have answered questions similar to these during the master planning process, but since a few years have passed, we want to be sure that what we design and propose for the Res reflects the current desires of the community. There are two ways to complete the survey:
  1. Use the link below to answer the questions about the swimming beach, what you hope to see in the new playground, how/when/where you access the Res… and a few more.  We think this will take you about 10-12 minutes to complete, but take the time that you need. Link https://www.surveymonkey.com/r/ArlingtonRes1 Or….
  2. Please answer as many of the questions as you can, as this information will help us improve the Res for you.  We appreciate your time and effort!
 
Below is current schedule for this design phase with important community input meetings highlighted. The Park and Recreation Commission thank you in advance for your insight, feedback, and participation in this important process.
Arlington Reservoir – Phase 2 Updated Project Schedule 24 June 2020 - REV
 
Project Award: May 2020
Design & Community Engagement Process: June – August 
Schematic Design document prep (for estimator, 2 weeks): June 30th
Public Engagement (crowd-sourcing): June 30th – July 22nd  
Public Meeting #1: Review survey results (Parks & Rec mtg): July 28th
Value Analysis/Construction Cost Estimates (2 weeks): July 15th
Design Development (6 weeks): July 1st – August 14th
Playground working group meeting #1: Week of July 6th
Playground working group meeting #2: Week of July 27th 
Public Meeting #2(Parks & Rec mtg): August 11th
Permitting (assume 2 hearings each Town):September – October
- Arlington ConComm filing date: August 20th 
- Arlington ConComm hearing date: September 3rd 
- Lexington ConComm filing date: Aug18th/September 1st
- Lexington ConComm hearing date: September 8th/21st
Construction Documentation (potential project 1: structures):September
Bid Phase (potential project 1: structures): October
Construction Phase (potential project 1: structures):November – April 2021
Construction Documentation (potential project 2: site work):September – November
Bid Phase (potential project 2: site work): December 2020
Construction Phase (potential project 2: site work): January – October 2021
**Phase work to open beach for 2021 season